PROJECT #5 Extending existing water pipe
Est.Cost: $82,000
ETA: 12 days
Length: 5,000 ft.
Contractor: Kennedy Pipeline Co.
With the rapid increase of population over the past few years new homes have
been being built more than ever and with that in mind Mission City is
extending their pre-laid water main another 5,000 feet to allow for the
maxiumum amount of new homes to be over this land
Kennedy Pipeline won the bid for this project with an estimated cost of
$82,000 and an E.T.A. of just 12 days. Above you can see them rushing to
get all their equipment on site the day before construction is set to begin
On the bright morning of day 1 Kennedy Pipeline crews began excavation
Not long after digging the end of the already pre-laid new water main was
located, this is where the 5,000 foot extention will be starting from
Once the water main tip had been located the excavation of the new pipeline
trench took off. While the big 984 excavator dug none stop and crews checked
the trench slope grade more equipment was delivered to the site to begin
the process of installing the new piping
Here's a close-up of one of the new 25' long pipe segments that will be used
The segments of pipe are unloaded with a DEERE 624J loader equipped with
a grapple and are then set into place along the side of the trench
Among the 624J that was delivered, for the use of unloading the pipe
segments, a CATERPILLAR 365C L excavator was also delivered, (the Kennedy
guys where all excited about this piece because it was the first time
they got to use it since it was just purchased by Kennedy Co. and delivered
straight from the factory) for lowering the new pipe segments
into place in the trench
Here you can eally see the project taking off as the 984 excavator continues
digging and the 365C L excavator begins lowering the new pieces of pipeline
Once the new pipeing was all in place and all the seal connections where dry
and inspected the CAT 365C L, with a wide bucket attached to its quick
coupler, crawled on top of the dirt pile along side the trench and
began the backfilling process as a HAMM compactor that was delivered
compacts the soil levels
Here's another shot as the backfilling of the trench nears completion
On exactly the twelve day the trench was completly backfilled and the job
was completed, right on schedule just as planned and expected
Construction of the new homes isn't set to begin for another few months
but within a year or so all this land will be covered with new
housing developments